Deokcheon Neighborhood Park Special Project: Announcement of the Urban Management Plan Change and Draft Strategic Environmental Impact Assessment Review


Busan Deokcheong-dong Long-term Unexecuted Park, Reborn as Private Special Project

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5

Deokcheong Neighborhood Park, located in Deokcheong-dong, Buk-gu, Busan, had been left unexecuted for over 20 years since its designation as an urban planning facility in 1972.

According to the 'Sunset System for Long-term Unexecuted Urban Planning Facilities', which came into effect on July 1, 2020, the likelihood of rampant development increases if the park becomes ineffective. To prevent this, the 'Private Park Development Special Project' has been initiated.

This project proceeds by creating and donating more than 70% of the park site as a park while installing non-park facilities such as residential buildings in less than 30% of the remaining area. This way, regional development and park creation are harmonized.

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5


Currently, a renegotiation for the strategic environmental impact assessment for changing the urban management plan regarding non-park facilities, namely housing construction, is in progress. This process is part of the administrative procedure to transition the existing 'Natural Green Zone' to '2nd Class General Residential Area.'





Project Delay and Scale Adjustment, Background of 'Renegotiation' for Strategic Environmental Impact Assessment

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5

The urban management plan for the 'Deokcheong Neighborhood Park Special Project' was agreed by Nakdong River Basin Environmental Agency on June 9, 2020. However, the project was significantly delayed due to the National Heritage Commission's delayed review and increased compensation costs. Consequently, the viability of the project has weakened, and adjustments to the scale of non-park facilities became necessary.



Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5

Importantly, although the agreement was completed, five years have passed without a change in the land use zone announcement. According to the Enforcement Decree of the 'Environmental Impact Assessment Act', if five years pass from the date of notification of the agreement, a 'renegotiation' of the strategic environmental impact assessment becomes necessary. Thus, the current renegotiation of the strategic environmental impact assessment is taking place.





From 'Natural Green Zone' to '2nd Class General Residential Area'... Plan for Non-Park Facilities

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5


The key content of the recently announced change in the urban management plan is the adjustment of the land use zone for the non-park area. This plan applies to the area of approximately 24,097㎡ in Deokcheong-dong, Buk-gu, Busan.

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5

The main content of the plan is to change the land use of the non-park area of 24,097㎡ located east of Deokcheong Neighborhood Park from the existing 'Natural Green Zone' to '2nd Class General Residential Area'. This is a measure for the conversion of land use for housing construction, which is a non-park facility, according to the private park special project, emphasizing the importance of balancing development scale and harmonizing with the park. This decision is expected to improve the living environment for local residents and enhance the connectivity with the park.





Construction of Apartments with Up to 29 Floors and 366 Units... Considering the View of Gupo Fortress



Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5

A new district unit plan zone for the Deokcheong Park area will be established on the non-park site of 24,097㎡. According to this plan, 96.4% of the total area, or 23,233㎡, is expected to be used as multi-family housing land, while the remaining 3.6%, or 864㎡, will be designated as public facility land to be used as a road.

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5

This multi-family housing site is expected to consist of 366 residential units in three buildings. The building is designed with three underground floors and 29 above-ground floors, with a building coverage ratio of 10.32% and a floor area ratio of 189.09%. Parking will be planned to accommodate 503 cars, exceeding the legal requirement of 409 spaces.

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5


Particularly important is the placement plan. Close to the site is the cultural asset area of Gupo Fortress. Reflecting this, the plan minimizes the disturbance to the terrain around Gupo Fortress and within the site while taking into consideration the historical significance and the view from the residential buildings, concentrating them on the north side.

Additionally, sufficient distance between residential buildings is secured to establish visual axes for viewing the park and external scenery. The height of the buildings has been planned to a maximum of 29 floors to create a natural skyline, reflecting that nearby apartments are between 29 and 35 floors. These elements focus on harmonizing with the characteristics of the area.





Future Procedures: Local Plan and Separate Assessment of Park Facilities

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5

This renegotiation is being conducted for the purpose of 'land use change'. Once this process is completed, decisions regarding the local plan zone for the housing construction project and related strategic environmental impact assessments and small-scale environmental impact assessments will proceed.



Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5

Meanwhile, the urban planning facility project for 'Deokcheong Neighborhood Park' was originally approved for the implementation plan on June 30, 2020, but construction has not commenced within five years. Therefore, there will be a process of 'change negotiation' for the small-scale environmental impact assessment before the implementation plan approval.





Deokcheong Neighborhood Park Special Project, Harmonizing Development Prevention and Residential Supply

Deokcheong Neighborhood Park Special Project - Buk-gu Deokcheong-dong San78-5


The special project for Deokcheong Neighborhood Park focuses on preventing indiscriminate development in response to the sunset system for long-term unexecuted urban parks and maintaining green spaces in urban areas. It also aims to supply housing by utilizing the land for non-park facilities.

The ongoing renegotiation for the strategic environmental impact assessment is considered a crucial administrative procedure as it is necessary due to the adjustments in the plan caused by project delays. It will be monitored whether the housing supply plans for 366 units, which consider the harmony with surrounding scenery such as Gupo Fortress, can proceed smoothly.





Deokcheong Neighborhood Park Special Project Urban Management Plan Decision (Change) (Renegotiation) Strategic Environmental Impact Assessment Draft Report

Chapter 2 Overview of the Basic Development Plan

2.1 Background and Objectives of the Plan



1. Background of the Plan
* Deokcheong Neighborhood Park, the site of this plan, has been a long-term unexecuted facility for over 20 years since its initial decision (December 30, 1972). In order to minimize rampant development due to the ineffectiveness of urban parks following the implementation of the 'Sunset System for Long-term Unexecuted Urban Planning Facilities' (July 1, 2020), the 'Private Park Development Special Project' was promoted.
* In promoting the 'Deokcheong Neighborhood Park Private Park Development Special Project' according to Article 21-2 of the 'Act on Urban Parks, Green Spaces, etc.' (special provisions regarding development activities in urban park sites), a change in land use is required for the construction of non-park facilities (housing construction project approval).

2. Objectives of the Plan
* Sequentially carry out administrative procedures necessary for implementing the 'Deokcheong Neighborhood Park Private Park Development Special Project' in accordance with relevant laws and regulations to facilitate smooth project progress, and to decide to change the land use plan (land use zone) appropriateness to the decided types and scales of non-park facilities.

image
2.3 Progress and Plans of the Project


December 1972: Initial decision of urban planning facility (Deokcheong Neighborhood Park) (Ministry of Construction and Transportation No. 1972-555)
October 1997: Initial decision of the urban planning facility (Deokcheong Neighborhood Park) park development plan (Busan Metropolitan City’s announcement No. 1997-259)
August 2017: Decision (Change) of the urban planning facility (Deokcheong Neighborhood Park) park development plan (Busan Metropolitan City’s announcement No. 2017-266)
December 2019: Decision (Change) of urban management planning (Facility: Park) and publication of topographic maps (Busan Metropolitan City’s announcement No. 2019-376)
February 2020: Designation of project implementing organization for urban planning facility (Park: Deokcheong Park) (Busan Metropolitan City’s announcement No. 2020-27)
June 8, 2021: Completion of negotiations for the strategic environmental impact assessment for the decision (change) of the urban management plan for the Deokcheong Neighborhood Park special project
June 30, 2022: Approval of the implementation plan for the urban planning facility (Park: Deokcheong Neighborhood Park) (Busan Metropolitan City’s announcement No. 2020-241)
November 2023: Decision (Change) of the urban planning facility (Deokcheong Neighborhood Park) park development plan (Busan Metropolitan City’s announcement No. 2023-406)
December 2024: Approval of the implementation plan (Change) for the urban planning facility (Park: Deokcheong Neighborhood Park) (Busan Metropolitan City’s announcement No. 2024-444)
April 2025: Application for decision (Change) of the urban management plan
June 2026: Approval of the implementation plan (Change) for the urban planning facility (Park: Deokcheong Neighborhood Park) (Busan Metropolitan City’s announcement No. 2025-231)
July 2027: Decision (Change) of the urban management plan (Deokcheong Park Development Plan) and publication of topographic maps (Busan Metropolitan City’s announcement No. 2025-268)
July 23 - August 6, 2028: Disclosure of the determination contents of strategic environmental impact assessment items (for 14 days)
* Busan Metropolitan City website, Environmental Impact Assessment Information Support System (EIASS)
August - September 2025: Public exhibition of draft strategic environmental impact assessment report and collection of opinions from relevant administrative agencies

image


image
2.4 Contents of the Plan


1. Overview of the Plan
1. Plan Name
Decision (Change) of the Urban Management Plan for the Deokcheong Neighborhood Park Special Project

2. Scope of the Plan
a) Spatial Scope
* Location: Area of Deokcheong Neighborhood Park, Buk-gu, Busan, San78-5 (refer to

)
* Area: 24,097㎡

b) Temporal Scope
* Reference Year: 2025
* Target Year: 2030

3. Project Implementer and Plan Establishment Authority
* Project Implementer: IPC Development Co., Ltd.
* Plan Establishment Authority: Busan Metropolitan City

4. Approval and Consultation Authorities
* Approval Authority: Busan Metropolitan City
* Consultation Authority: Nakdong River Basin Environmental Agency

2. Contents of the Plan
1. Decision to Change the Urban Management Plan (Land Use Zone)
* Planning to change the land use zone for non-park areas in accordance with the review and decision of the Busan Metropolitan City’s National Heritage Commission (Monument Division) and Urban Planning Committee.
* Planning to change the land use zone for the non-park area (24,097㎡) on the east side of Deokcheong Neighborhood Park while comprehensively considering harmony with the park and the urban landscape.
* Planning to change the land use zone from natural green zone to 2nd Class General Residential Area to prevent excessive development scale.

Land Use Zone Determination (Change) Report

ClassificationInitial (㎡)Change (㎡)After Change (㎡)Area (㎡)Composition Ratio (%)
Residential Area Total-Increase) 24,09724,09724,097100.0
2nd Class General Residential Area-Increase) 24,09724,09724,097100.0
Green Area Total24,097Decrease) 24,097---
Natural Green Zone24,097Decrease) 24,097---

Reason for Land Use Zone Determination (Change)



LocationLand Use ZoneArea (㎡)Floor Area Ratio (%)Reason for Change
Area of Buk-gu Deokcheong-dong San78-5Natural Green Zone → 2nd Class General Residential Area24,097200% or lessChange in land use for non-park facilities (housing construction land) due to the implementation of private park development special project
image
image
image
image



2. Non-Park Project Plan (Draft)
a) District Unit Plan Zone and District Unit Plan (Draft)
(1) Designation of the district unit plan zone (Draft)
* Planning to designate a district unit plan zone that complies with the '2040 Busan Urban Basic Plan'.
* Planning to designate a district unit plan zone for effective and systematic development and management of the non-park facility land under the Deokcheong Neighborhood Park Private Park Development Special Project in accordance with Article 21-2 of the 'Act on Urban Parks, Green Spaces, etc.' (special provisions regarding development activities in urban park sites).
* Planning to delineate the district unit plan zone with the same boundaries as the changed land use zone.

District Boundary Setting

ClassificationCriteria for Setting District BoundariesComments
① East SideBoundary of urban planning facility (Jongno 1-67 line)Uiseong Road
② North SideReligious facility (Suwon Shinwon) and consideration of terrain
③ West SideSafe distance from cultural asset area (Deokpo Swaecheong)
④ South SideConsideration of terrain

Decision (Draft) on District Unit Plan

ClassificationMap Notation NumberZone NameLocationArea (㎡)Comments
Newly EstablishedADeokcheong Park District Unit Plan ZoneArea of Buk-gu Deokcheong-dong San78-5- → Increase) 24,09724,097

Reason for Decision (Draft) on District Unit Plan



Zone NameLocationDecision DetailsReason for Decision
Deokcheong Park DistrictArea of Buk-gu Deokcheong-dong San78-5New district unit plan zone - A = 24,097㎡To facilitate effective and systematic development and management of non-park facility land under the Deokcheong Neighborhood Park Private Park Development Special Project according to Article 21-2 of the 'Act on Urban Parks, Green Spaces, etc.' (special provisions regarding development activities in urban park sites).
image
image


b) Building Plan (Draft)
(1) Overview of the Building
* This planning site is for multi-family housing (apartments) consisting of three buildings with a total of 366 units.
* The site area is 23,233㎡, and the building area is planned at 2,398.5㎡, with a building coverage ratio of 10.32%.
* The total floor area is planned to be 67,777.27㎡, consisting of 43,930.81㎡ above ground and 23,846.46㎡ below ground, resulting in a floor area ratio of 189.09%.
* The height of the building (number of floors) is planned for three underground floors and 29 above-ground floors.
* The planned number of parking spaces is set at 503, which is 122.98% compared to the legal requirement (409 spaces).

Building Plan (Draft)

ClassificationPlan Details
LocationArea of Buk-gu Deokcheong-dong San78-5
Land Use Zone2nd Class General Residential Area
Site Area (㎡)23,233㎡ (excluding donation area of 864㎡)
Usable Site Area (㎡)23,233㎡
UseMulti-family housing (apartments) and auxiliary facilities
Building Area (㎡)2,398.50㎡
Total Floor Area (㎡)43,930.81㎡ above ground / 23,846.46㎡ below ground / Total 67,777.27㎡
Building Coverage Ratio (%)10.32
Floor Area Ratio (%)189.09
Scale3 underground floors, 29 above-ground floors, total of 366 units
Legal Number of Parking Spaces409 spaces
Planned Number of Parking Spaces503 spaces (122.98% compared to legal requirement)


image
image
image
image
image


image
image
image
image
Deokcheong Neighborhood Park: 93 San, Deokcheong-dong, Buk-gu, Busan





#DeokcheongNeighborhoodParkSpecialProject, #BusanDeokcheongdong, #PrivateParkSpecialProject, #DeokcheongPark, #DeokcheongParkApartments, #DeokcheongdongDevelopment, #BusanBukgu, #LongTermUnexecutedPark, #ParkSunsetSystem, #StrategicEnvironmentalImpactAssessment, #ChangeOfLandUseZone, #2ndClassGeneralResidentialArea, #NaturalGreenZone, #GupoFortress, #DeokcheongParkDistrictUnitPlan, #BusanApartments, #BusanRealEstate, #UrbanManagementPlan, #HousingConstructionProject, #IPCDevelopment, #BusanMetropolitanCity, #NakdongRiverBasinEnvironmentalAgency, #ParkDevelopment, #PreventionOfIndiscriminateDevelopment, #NonParkFacilities, #VisualAxes, #Skyline, #EnvironmentalImpactAssessment, #RealEstateNews, #DevelopmentProspects


Frequently Asked Questions (FAQ)

Q. What is the Deokcheong Neighborhood Park Special Project and why was it initiated?
The Deokcheong Neighborhood Park Special Project was promoted as a private park development special project to prevent rampant development of long-term unexecuted urban parks.

The Deokcheong Neighborhood Park has been left unexecuted for over 20 years since its designation in 1972, and the risk of rampant development increased with the enforcement of the long-term unexecuted urban planning facility sunset system in 2020. To prevent this and to harmonize the preservation of green spaces in urban areas with the provision of housing, the 'Private Park Development Special Project' was initiated, proceeding with the plan of creating over 70% of the park area as a park while installing non-park facilities such as residential buildings in less than 30% of the remaining area.

Q. What is the reason for changing the urban management plan and renegotiating the strategic environmental impact assessment?
The negotiation was delayed due to project delays and the 5-year period expiring, necessitating the renegotiation of the strategic environmental impact assessment.

The Deokcheong Neighborhood Park Special Project has been delayed due to delays in the deliberation by the National Heritage Commission and increased compensation costs, and the validity period of the existing report expired after 5 years. Therefore, a renegotiation of the strategic environmental impact assessment is underway to carry out the necessary administrative procedures for changing land use to prevent delays.

Q. What are the main contents of the land use change?
The plan is to change the non-park area of 24,097㎡ from natural green zone to 2nd Class General Residential Area.

About 24,097㎡ of the non-park area east of Deokcheong Neighborhood Park is planned to be converted from the existing natural green zone to 2nd Class General Residential Area for housing construction. This decision aims to facilitate the supply of residential facilities in accordance with the private park special project while adjusting the development scale and promoting harmony between the park and residential areas, thereby improving the living environment for residents and increasing the connectivity with the park.

Q. What are the scale and characteristics of the new residential facilities to be developed?
It is planned to construct apartments with 3 buildings and 366 units, along with parking for 503 vehicles, with underground 3 floors and above ground 29 floors.

The project involves building 366 units of apartments in 3 buildings on approximately 23,233㎡ of non-park land, designed with a building coverage ratio of 10.32% and a floor area ratio of 189.09%. The parking facility is planned to accommodate more than the legal requirement with 503 spaces, designed to align harmoniously with nearby apartment buildings, adjusting the placement of the residential buildings considering views of Gupo Fortress, historical significance, and the establishment of visual axes.

Q. What will be the future procedures for project promotion?
Renegotiation of the strategic environmental impact assessment will be followed by decisions on the district unit plan and small-scale environmental impact assessments.

After the renegotiation of the strategic environmental impact assessment is completed, decisions on the district unit plan for housing construction project approval will be made, and additional procedures for related strategic environmental impact assessments and small-scale environmental impact assessments will take place. Furthermore, before the implementation plan approval, amendments to the environmental impact assessment will also be processed to ensure smooth project advancement through sequential administrative procedures.


다음 이전